U.S. Tsubaki was in need of additional office and production space as well as a laboratory area to perform engine timing chain testing.
Design/Build Engineering and Permitting
- Complete site design including planning and permitting approvals
- Developed complete project specifications and plans to complement their existing facility
Construction of a 120,000 SF Butler Building including the following:
- Site Work
- Foundation
- Steel Erection
- Exterior Split Face Block
- Turnkey pre-engineered building by Butler Manufacturing
- Epoxy Flooring
- Storefront Glass
- Automotive testing lab
- HVAC
- Plumbing
- Electrical
35,000 SF of two story office space with 5,000 SF of laboratory and 80,000 SF of manufacturing space
Location: Chicopee, MA
Engineering: Full Design Build Services
Market Sector: Industrial
Year started: 2017
Duration: 12 months