Covestro
Industrial
Renovation of Existing Shipping and Receiving, Break Room, Locker Rooms, and Bathrooms.
- Set up containment around project with negative air to prevent disturbance to production.
- Shore and Demo existing load bearing masonry walls for expansion of existing spaces.
- Foundation
- New masonry walls.
- New structural steel mezzanine.
- Epoxy Flooring, LVT Flooring, and Carpet Tile.
- Storefront Glass
- Millwork
- HVAC incorporated into existing BIM System.
- Plumbing
- Electrical
Location: Whately, MA
Engineering: Hill Engineers, Architects, and Planners. 50 Depot St, Dalton, MA.
Market Sector: Industrial
Year started: 2019
Duration: 4.5 months. Earned Early Completion Bonus for finishing before scheduled completion.